Q. Joint sighting committee shall inspect the visibility of signals once in

Correct Answer

3 months

More Questions on Indian Railway

  • Q. Where is the Research, Design and Standard Organisation situated?
    A)Pune
    B)Lucknow
    C)Bangalore
    D)New Delhi
    Answer: Lucknow
  • Q. In automatic areas when all signals have failed and communication is available, the driver is issued ________ as authority to proceed.
    A)T/C-912
    B)T/B-912
    C)T/D-912
    D)None of these
    Answer: T/D-912
  • Q. Goods warning board will be provided from FSS in BG at
    A)560 meters
    B)1400 meters
    C)1000 meters
    D)None of these
    Answer: 1400 meters
  • Q. While shunting a complete train from one line to the other, ________ shall be present in the brakevan.
    A)ALP
    B)Driver
    C)Guard
    D)None of these
    Answer: Guard
  • Q. Which of the following is the largest marshalling yard in India (also the longest in Asia)?
    A)Itarsi
    B)Mughalsarai
    C)Mathura
    D)Guntakal
    Answer: Mughalsarai
  • Q. How many stations to be redeveloped through PPP?
    A)350
    B)100
    C)200
    D)600
    Answer: 600
  • Q. In case of goods train without brake van, Guard is exempted from ________.
    A)Whistling
    B)ARS
    C)Tail Lamp
    D)None of these
    Answer: ARS
  • Q. Marshalling rules of passenger train are framed by ________.
    A)DRM
    B)DOM
    C)COM
    D)AOM
    Answer: COM
  • Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
    A)Shunt
    B)Repeating
    C)Call-on
    D)None of these
    Answer: Repeating
  • Q. Standard time is set at all station every day ________ Hours
    A)16
    B)10
    C)15
    D)None of these
    Answer: 16
  • Q. Maximum height above rail level for a low passenger platform in BG is
    A)840 mm
    B)455 mm
    C)760 mm
    D)None of these
    Answer: 455 mm
  • Q. In case of ACP, Guard of EMU shall give ________ bell.
    A)0-00-00
    B)00-00-00
    C)00-0-00
    D)000-0-00
    Answer: 00-0-00
  • Q. When the signal is blank in MACLS system, it is treated as showing ________ aspect.
    A)Defective
    B)Restricted
    C)Most restricted
    D)Noe of these
    Answer: Most restricted
  • Q. If the G marker Gate signal is at ON, Loco pilot may pass it after stopping for 01 minute by day and ________ minutes by night.
    A)8
    B)5
    C)2
    D)4
    Answer: 2
  • Q. Reference of ________ is written by the side of the Rule if the Rule is corrected.
    A)No. and Item No. Correction Slip
    B)Number Slip
    C)Item Number
    D)None of these
    Answer: No. and Item No. Correction Slip
  • Q. Where is the extreme north of India a railway station?
    A)Pathankot
    B)Jammu Tawi
    C)Baramulla
    D)Guwahati
    Answer: Baramulla
  • Q. Presentation of the first ever railway budget in India held in
    A)1925
    B)1853
    C)1888
    D)1905
    Answer: 1925
  • Q. Hand shunting outside section in gradient ________ is prohibited except with DRM permission.
    A)ST 1-800
    B)ST 1-600
    C)ST 1-700
    D)None of these
    Answer: ST 1-600
  • Q. What will be the speed of second train running on T/C 602?
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)Normal speed
    Answer: Normal speed
  • Q. Which Zone is the largest in Indian Railways?
    A)Eastern Railway
    B)Central Railway
    C)Northern Railway
    D)Western Railway
    Answer: Eastern Railway