- Q. What will be the maximum speed of train passing through loop line of a station name suffixed by “II” in working time table.
A)25 kmph
B)10 kmph
C)15 kmph
D)Normal speed
Answer: 15 kmph
- Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
A)Block sectiond
B)Next whole block section
C)Back whole block section
D)None of these
Answer: Next whole block section
- Q. Fly shunting will take place in
A)Flat Yard
B)Hump Yard
C)Gravity Yard
D)None of these
Answer: Hump Yard
- Q. While clearing the load with an invalid brake power certificate, if train examiner is not available, Loco Pilot and Guard shall ensure safety of the train and take the train upto ________.
A)Executive
B)Examine
C)Next Examine
D)None of these
Answer: Next Examine
- Q. BSLB determines the limits of block section and ________ .
A)Station Limit
B)Block Section
C)Station Section
D)None of these
Answer: Station Section
- Q. On DL the speed of the train during total interruption of communication is ________ kmph when the view ahead is clear during day and night.
A)25
B)20
C)15
D)None of these
Answer: 25
- Q. Where was the B.B.C.I locomotive started?
A)Boriville
B)Jamalpur
C)Parel
D)Hyderabad
Answer: Parel
- Q. Reference of ________ is written by the side of the Rule if the Rule is corrected.
A)No. and Item No. Correction Slip
B)Number Slip
C)Item Number
D)None of these
Answer: No. and Item No. Correction Slip
- Q. Ruling gradient of the division is mentioned in the ________.
A)SOR
B)SWR
C)WTT
D)None of these
Answer: WTT
- Q. Hand shunting speed is ________
A)8 kmph
B)5 kmph
C)10 kmph
D)None of these
Answer: 5 kmph
- Q. Normal condition of automatic stop signal is ________.
A)Yellow
B)Red
C)Green
D)None of these
Answer: Green
- Q. During TFC in single line section what authority to proceed will be served to driver of Dn train during return.
A)TH-602
B)T/A-602
C)TG-602
D)TB-602
Answer: TH-602
- Q. A jumper is remote control and is used for ________.
A)Control on Light, Fan etc.
B)Light
C)Fans
D)None of these
Answer: Control on Light, Fan etc.
- Q. At a station in gradient in 1-260 or steeper, during shunting the Engine must be on the ________ gradient.
A)Both
B)UP
C)Falling
D)None of these
Answer: UP
- Q. Standard time is set at all station every day ________ Hours
A)16
B)10
C)15
D)None of these
Answer: 16
- Q. Goods warning board will be provided from FSS in BG at
A)560 meters
B)1400 meters
C)1000 meters
D)None of these
Answer: 1400 meters
- Q. A separate Railway Budget, which is different from the General Budget, was first introduced in 1924 on the basis of recommendations of the 10 – member:
A)Rail Budget Committee
B)Acworth Committee
C)Srinivas Shastri Committee
D)Sultan Committee
Answer: Acworth Committee
- Q. The White light in point indicator indicates?
A)Pass run through
B)Loop line is set
C)Main line set
D)All is right
Answer: Main line set
- Q. Air pressure in the engine and brake van of a goods train with 58 N Boxes shall be 5.0 kg/cm2 and ________ respectively.
A)4.5 kg/cm2
B)4.1 kg/cm2
C)4.2 kg/cm2
D)4.7 kg/cm2
Answer: 4.7 kg/cm2
- Q. Maximum height above rail level for a low passenger platform in BG is
A)840 mm
B)455 mm
C)760 mm
D)None of these
Answer: 455 mm