Q. Warning boards for neutral section shall be fixed at a distance of

Correct Answer

500 and 250 meters

More Questions on Indian Railway

  • Q. When was the Jammu City appeared on the map of Indian Railway?
    A)1967
    B)1956
    C)1963
    D)1965
    Answer: 1965
  • Q. The speed of a Trolley is
    A)15 kmph
    B)20 kmph
    C)8 kmph
    D)None of these
    Answer: 15 kmph
  • Q. What is the maximum speed of a train Ist train dispatched after introduced TSL on double line section?
    A)15 kmph
    B)30 kmph
    C)25 kmph
    D)Normal speed
    Answer: 25 kmph
  • Q. Guard’s assistance is required by LP.
    A)0
    B)0
    C)0
    D)____
    Answer: 0
  • Q. Repeating signal shows ________ light in ON condition.
    A)Green
    B)Red
    C)Yellow
    D)None of these
    Answer: Red
  • Q. How much minimum BP pressure is reduce to require to apply brake in a goods train?
    A)1.00 kg/cm2 to 1.50 kg/cm2 D. 2.00 kg/cm2or more
    B)Less than1.0 kg/cm2 B. 1.00 kg/cm2 to 2.00 kg/cm2 C. 1.00 kg/cm2 to 1.50 kg/cm2 D. 2.00 kg/cm2or more
    C)1.00 kg/cm2 to 2.00 kg/cm2 C. 1.00 kg/cm2 to 1.50 kg/cm2 D. 2.00 kg/cm2or more
    D)
    Answer: Less than1.0 kg/cm2 B. 1.00 kg/cm2 to 2.00 kg/cm2 C. 1.00 kg/cm2 to 1.50 kg/cm2 D. 2.00 kg/cm2or more
  • Q. If the IBS is defective and advanced starter is working, SM shall issue ________ authority with private number of next station to pass IBS.
    A)T/369(4b)
    B)T/369(3b)
    C)T/369(2B)
    D)T/369(5b)
    Answer: T/369(3b)
  • Q. Station section available in which Class of Station?
    A)C-Class
    B)A-Class
    C)B-Class
    D)D-Class
    Answer: B-Class
  • Q. Normally material train will work during ________.
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. During total failure of communication on a single line system, asking line clear of 4 trains at a time what will be the speed of next train?
    A)25/10 kmph
    B)15/8 kmph
    C)25/8 kmph
    D)25/12 kmph
    Answer: 25/8 kmph
  • Q. Information of caution notice stations is given in ________.
    A)Both A or B
    B)WTT
    C)Working time table
    D)None of these
    Answer: Both A or B
  • Q. To attach the 12 coach EMU rake, ________ units are to be attached.
    A)8
    B)5
    C)6
    D)4
    Answer: 4
  • Q. In which year Indian Railway was nationalized?
    A)1952
    B)1947
    C)1951
    D)1955
    Answer: 1951
  • Q. Except ________ signal, cabin master shall not show any other signal from his cabin during shunting.
    A)Red hand signal
    B)Yellow signal
    C)Green signal
    D)None of these
    Answer: Red hand signal
  • Q. Staff of ________ department shall protect the material train while working in block section.
    A)Engineering
    B)Operation
    C)C & W
    D)None of these
    Answer: Engineering
  • Q. Last stop signal means the ________ of a station controlling the entry of trains into the next block section.
    A)Call-on Signal
    B)Fixed stop signal
    C)Hand Signal
    D)None of these
    Answer: Fixed stop signal
  • Q. What should be done by guard if train entering in block section without authority to proceed?
    A)Protect the Train
    B)Stop the Train
    C)Inform to SM
    D)All of above
    Answer: All of above
  • Q. What is the maximum speed of 140 ton diesel hydraulic crane?
    A)140 kmph
    B)75 kmph
    C)100 kmph
    D)160 kmph
    Answer: 75 kmph
  • Q. In push button token less territory, before starting the train with for T/369(1) during signal failure at station in advance, SM to get ________ from that station.
    A)Both
    B)PN
    C)Non-PN
    D)None of these
    Answer: PN
  • Q. The use of block instrument shall be governed by special instructions to be issued with the prior approval of
    A)CSO
    B)Railway Board
    C)CRS
    D)None of these
    Answer: CRS