- Q. Launched three Trains to improve Quality of Travel (for reserved passengers), these are:
A)Dirubhargh, Sahayak and Humsafar
B)Humsafar, Tejas and Uday
C)Tejas, Antyodaya and Gatiman
D)Sahayak,Antyodaya and Gatiman
Answer: Humsafar, Tejas and Uday
- Q. When the points are set for main line, point indicator shows white target by day and ________ Light by night.
A)Yellow
B)Red
C)Green
D)White
Answer: White
- Q. What will be the prescribed form for DMT Block?
A)E/223
B)T/409
C)T/806
D)E/233
Answer: E/223
- Q. Railway Staff College is situated at
A)Chennai
B)Bangalore
C)Secunderabad
D)Vadodara
Answer: Vadodara
- Q. Accident drill is to be conducted once in ________ if no real accident occurs during this period.
A)01 month
B)04 month
C)02 month
D)03 Months
Answer: 02 month
- Q. To admit the train on loop line, generally the far end points are to be ser for ________.
A)Both
B)Loop line
C)Main line
D)None of these
Answer: Main line
- Q. The speed of a Trolley is
A)15 kmph
B)20 kmph
C)8 kmph
D)None of these
Answer: 15 kmph
- Q. While stabling box load, hand brakes of ________ wagons at both ends shall be pinned down.
A)7 - 7
B)8 - 8
C)6 - 6
D)8 - 8
Answer: 6 - 6
- Q. Headquarters of which one among the following Railway Zones in India is situated at the highest elevation from the mean sea level?
A)South Western Railway
B)East Central Railway
C)South Eastern Railway
D)West Central Railway
Answer: South Western Railway
- Q. The additional Hours in the case of Gate man C saloon attendant, care takers will be ________
A)24 Hours
B)12 Hours
C)08 Hours
D)16 Hours
Answer: 24 Hours
- Q. Calling on signal shows ________ light in off position in two aspect signalling system.
A)Green
B)White
C)RED
D)Yellow
Answer: Yellow
- Q. When water level is just above top of rail speed of electric locomotive shall apply ?
A)15 kmph
B)5 kmph
C)10 kmph
D)20 kmph
Answer: 10 kmph
- Q. Which authority shall be received from station in rear to pass defective home signal?
A)T-409
B)T-369(3b)
C)T-369(1)
D)Simple memo
Answer: T-369(1)
- Q. When a train is working on T/D912 in automatic block in system, the train must be piloted into the station during reception by
A)T/369(1)
B)T/369(3b)
C)T/369(2)
D)T/409
Answer: T/409
- Q. Shatabdi Express train was started in ________.
A)1990
B)1984
C)1988
D)1985
Answer: 1988
- Q. Marshalling rules of passenger train are framed by ________.
A)DRM
B)DOM
C)COM
D)AOM
Answer: COM
- Q. The distance between two automatic signals is normally
A)3 km
B)2 km
C)1 km
D)None of these
Answer: 1 km
- Q. If the driver does not receive all right signal from the guard, he must call by giving.
A)On long
B)Two sharp whistles
C)One long one short
D)None of these
Answer: Two sharp whistles
- Q. The speed of the train over neutral section shall not be less than ________ kmph
A)40
B)20
C)30
D)None of these
Answer: 30
- Q. Which of the following is / are Union Subjects as per seventh schedule of the Constitution of India? 1)Armed Forces 2)Paramilitary Forces 3)Railway Police 4)Cantonment Areas Select the correct option from the codes given below:
A)Only 1, 2 & 4
B)Only 1 & 2
C)Only 1, 2 & 3
D)1, 2, 3 & 4
Answer: Only 1, 2 & 4