More Questions on Indian Railway
- Q. Shutting signal in the color light signal system under the starter of which light is visible in the on-condition?
A)Single white
B)Yellow
C)Two White parallel
D)No light
Answer: No light
- Q. Number of the Reminder caution order is ________.
A)T/C 410
B)T/A 409
C)T/B 409
D)None of these
Answer: T/B 409
- Q. When a front portion of a parted train gives one long one short one long one short whistle, SM to wave ________ signal four times above head from side to side and acknowledge.
A)Yellow
B)RED
C)Green
D)None of these
Answer: RED
- Q. The manufacturing of steam engine in Chittranjan Locomotive Works was stopped in
A)1972
B)1974
C)1961
D)1973
Answer: 1972
- Q. BP in the Guard cab of EMU shall be ________ kg/cm2 and Motor mans cab shall be 4.6 kg/cm2.
A)4
B)4.2
C)4.01
D)4.6
Answer: 4.6
- Q. For overhauling of lever frame at stations, ________ is prepared jointly by Sr. DOM and DSTE for working of trains.
A)Both
B)Temporary Working Order.
C)Permanent working order.
D)None of these
Answer: Temporary Working Order.
- Q. How many copies of caution order shall be prepared for a train provided with banking engine?
A)5
B)3
C)4
D)None of these
Answer: 5
- Q. Impact speed of shunting of one box wagon is ________ km/h.
A)6
B)2
C)5
D)8
Answer: 5
- Q. The banner flag is a ________
A)Both of these
B)Temporary stop signal
C)Permanent stop signal
D)None of these
Answer: Temporary stop signal
- Q. Which marker is available in repeating signal?
A)P-Marker
B)G-Marker
C)C-Marker
D)R-Marker
Answer: R-Marker
- Q. What will be the maximum speed of B-Class ODC in Broad guage?
A)40 kmph
B)15 kmph
C)25 kmph
D)75 kmph
Answer: 40 kmph
- Q. In automatic block system SL, the minimum equipment of signal shall be
A)Home, Starter, Advance Starter
B)Home, Starter
C)Distance Home Starter
D)None of these
Answer: Home, Starter
- Q. The minimum BP pressure is requiring on engine before continuity test is?
A)5.8 kg/cm2 D. 5.00 kg/cm2
B)4.8 kg/cm2 B. 6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
C)6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
D)5.00 kg/cm2
Answer: 5.00 kg/cm2
- Q. How many surrounding area may be sealed from fire in case of leakage in LPG tank wagon?
A)1500 meters
B)200 meters
C)1000 meters
D)2000 meters
Answer: 1000 meters
- Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
A)5
B)10
C)20
D)None of these
Answer: 10
- Q. Which of the following is the largest zone in terms of route kilometers?
A)Northern Railways
B)Western Railways
C)Eastern Railways
D)Southern Railways
Answer: Northern Railways
- Q. Tower wagon shall run as per the rules of working of ________.
A)Passengers
B)Wagon
C)Train
D)None of these
Answer: Train
- Q. During TSL working in thick and foggy weather, speed of the first train shall not exceed ________ km/h.
A)15 km
B)8 km
C)10 km
D)25 km
Answer: 25 km
- Q. When ISMD attached train is allowed to run through on PF line the speed must be
A)10 kmph
B)5 kmph
C)8 kmph
D)None of these
Answer: 5 kmph
- Q. Information of caution notice stations is given in ________.
A)Both A or B
B)WTT
C)Working time table
D)None of these
Answer: Both A or B