- Q. What is the maximum speed in block section during thick & foggy weather?
A)15 kmph
B)30 kmph
C)60 kmph
D)Not to move
Answer: 60 kmph
- Q. Joint sighting committee shall inspect the visibility of signals once in
A)6 months
B)A month
C)3 months
D)None of these
Answer: 3 months
- Q. What is the speed of A class ODC in BG?
A)40 kmph
B)15 kmph
C)25 kmph
D)Normal speed
Answer: Normal speed
- Q. In automatic block area SL. The LSS shall not be taken off unless the line is clear upto
A)Automatic stop signal+180 Meters
B)Next automatic stop signal
C)Automatic stop signal+120 Meters
D)None of these
Answer: Next automatic stop signal
- Q. In MACLS system, if approach signal becomes blank, ________ authority is issued from the station in rear.
A)T/407
B)T/409
C)T/408
D)T/406
Answer: T/409
- Q. Headquarters of which one among the following Railway Zones in India is situated at the highest elevation from the mean sea level?
A)South Western Railway
B)East Central Railway
C)South Eastern Railway
D)West Central Railway
Answer: South Western Railway
- Q. High flood level mark shall be painted in
A)Blue
B)Red
C)White
D)None of these
Answer: Red
- Q. When the SM receive a message from local authorities fro unsafe condition of river bunds he must issue caution order with speed ________ kmph during day.
A)5
B)15
C)20
D)None of these
Answer: 15
- Q. Notice station caution order No. is ________
A)T/C-409
B)T/409
C)T/B-409
D)None of these
Answer: T/409
- Q. In case of ACP Guard shall proceed towards the front from ________ side.
A)Back
B)Left
C)Right
D)Noe of these
Answer: Left
- Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of BP pressure in the engine.
A)5
B)4
C)2
D)8
Answer: 5
- Q. Continuity test is to be done.
A)_____00
B)0
C)0
D)00------
Answer: 00------
- Q. To send the assisting engine into obstructed block section T/A 602 authority is issued ________ and the speed of engine shall be ________.
A)15/10 km/h
B)25/10 km/h
C)20/10 km/h
D)None of these
Answer: 15/10 km/h
- Q. The headquarters of North – East Frontier Railway (NFR) is
A)Chennai
B)Kolkata
C)Maligaon (Guwahati)
D)Gorakhpur
Answer: Maligaon (Guwahati)
- Q. What type of speed restriction imposed for loco pilot when at LC gate communication not available between Gateman & Station Master ?
A)8 kmph
B)15 kmph
C)10 kmph
D)Normal
Answer: 10 kmph
- Q. Repeating signal shows ________ light in ON condition.
A)Green
B)Red
C)Yellow
D)None of these
Answer: Red
- Q. Signal sighting committee shall submit its report on form ________.
A)T/101 B
B)T/103 B
C)T/102 B
D)None of these
Answer: T/102 B
- Q. Track maintenance machine is permitted to work during
A)Day clear weather
B)Day
C)Day and Night
D)None of these
Answer: Day and Night
- Q. Normally maximum gradient in station yards in BG is (at present)
A)1 in 1000
B)1 in 260
C)1 - 400
D)None of these
Answer: 1 - 400
- Q. Station working rules of an interlocked station is prepared by Sr. DOM and ________.
A)Sr. DSTE
B)DOM
C)COM
D)None of these
Answer: Sr. DSTE