Q. Hand shunting of vehicles in gradients ________ is totally prohibited

Correct Answer

1 in 400 or Steeper

More Questions on Indian Railway

  • Q. What is the speed of a train after normalized in OHE supply immediate after tripping?
    A)40/15 kmph
    B)60/30 kmph
    C)35/20 kmph
    D)Normal speed
    Answer: 35/20 kmph
  • Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
    A)Shunt
    B)Repeating
    C)Call-on
    D)None of these
    Answer: Repeating
  • Q. Written authority received to pass approach stop signal.
    A)25 kmph
    B)10 kmph
    C)15 kmph
    D)Normal speed
    Answer: 15 kmph
  • Q. Where was the B.B.C.I locomotive started?
    A)Boriville
    B)Jamalpur
    C)Parel
    D)Hyderabad
    Answer: Parel
  • Q. In Automatic areas when there are no signals and communication, the speed of the train is ________ kmph while working on T/B 912 during day.
    A)15
    B)25
    C)20
    D)10
    Answer: 25
  • Q. When a running line is occupied ________ entry must be made in TSR.
    A)Yellow Ink
    B)Red Ink
    C)Green Ink
    D)None of these
    Answer: Red Ink
  • Q. In case of defective home signal of C’ class station, T/369(3b) authority is issued on which ________ of the staion in advance is written.
    A)Authority
    B)Private Number
    C)Cuation Number
    D)None of these
    Answer: Private Number
  • Q. Where is the wheel and axle plant of Indian Railways situated ?
    A)Mysore
    B)Chennai
    C)Bangalore
    D)Chitradurga
    Answer: Bangalore
  • Q. ________ is measured with the help of anemometer.
    A)Both
    B)Wind
    C)Velocity
    D)None of these
    Answer: Both
  • Q. The distance between two automatic signals is normally
    A)3 km
    B)2 km
    C)1 km
    D)None of these
    Answer: 1 km
  • Q. In which of the following cities, the first subway train was started?
    A)Kolkata
    B)Mumbai
    C)Delhi
    D)Chennai
    Answer: Kolkata
  • Q. “C” class ODC is run with the permission of ________.
    A)Head Quarter
    B)DOM
    C)CRS
    D)None of these
    Answer: CRS
  • Q. Gorakhpur which has the longest railway platform in the world is located in which of the following states?
    A)Uttar Pradesh
    B)Odisha
    C)West Bengal
    D)Chhattisgarh
    Answer: Uttar Pradesh
  • Q. Adequate distance mentioned in the automatic block system is ________ meters.
    A)105
    B)110
    C)120
    D)115
    Answer: 120
  • Q. Maximum speed of trains during thick & foggy weather in automatic block system is ________ kmph when signal is showing double yellow.
    A)25
    B)30
    C)20
    D)50
    Answer: 30
  • Q. Hand shunting outside section in gradient ________ is prohibited except with DRM permission.
    A)ST 1-800
    B)ST 1-600
    C)ST 1-700
    D)None of these
    Answer: ST 1-600
  • Q. Not more than ________ persons including trollyman shall go on a 6 HP motory trolly.
    A)9
    B)10
    C)3
    D)4
    Answer: 10
  • Q. Which authority shall be received to perform shunting beyond LSS at station of double line equipped with
    A)T/A 602
    B)T-806
    C)T/A 802
    D)T-806 A
    Answer: T-806
  • Q. When a Train carrying passengers does not arrive within ________ minutes plus running time. The SM must take action.
    A)15
    B)10
    C)20
    D)None of these
    Answer: 10
  • Q. Speed of second train during temporary single line working is ________.
    A)Both
    B)Normal
    C)Abnormal
    D)None of these
    Answer: Normal