Q. Depot in-charge is responsible to test the detonators once in ________.

Correct Answer

Year

More Questions on Indian Railway

  • Q. Trolley caution order no is ________.
    A)600
    B)400
    C)500
    D)800
    Answer: 400
  • Q. Competency certificate of the gateman of interlocked engineering gate is issued by
    A)SSE/C & W
    B)SSE/P.way
    C)SSE/Sig.
    D)None of these
    Answer: SSE/P.way
  • Q. Which authority shall be received to perform shunting beyond LSS at station of double line equipped with
    A)T/A 602
    B)T-806
    C)T/A 802
    D)T-806 A
    Answer: T-806
  • Q. Distance between two automatic signals is called as ________.
    A)Signalling Section
    B)Block section
    C)Mid Section
    D)None of these
    Answer: Signalling Section
  • Q. When the points are set for loop line, the point indicator shows no target by day and ________ Light by night.
    A)Yellow
    B)Red
    C)Green
    D)White
    Answer: Green
  • Q. When an accident occurs the GDR must their report to next SM in form.
    A)ACC5
    B)ACC1
    C)ACC2
    D)ACC3
    Answer: ACC3
  • Q. Target time for ARME from double exit siding is?
    A)45 minutes
    B)20 minutes
    C)30 minutes
    D)60 minutes
    Answer: 20 minutes
  • Q. ________ must be issued during thick or foggy weather.
    A)Reminder Caution Order
    B)Caution Order
    C)Nil Caution Order
    D)Minimum Caution Order
    Answer: Caution Order
  • Q. When was the first train in India started?
    A)1853
    B)1851
    C)1852
    D)1854
    Answer: 1853
  • Q. While ordering ART/MRV each siren shall be sounded for ________ seconds.
    A)43
    B)41
    C)42
    D)45
    Answer: 45
  • Q. When VP vehicles are attached in a goods train the maximum number of VPvehicle in one group is
    A)8
    B)10
    C)6
    D)None of these
    Answer: 6
  • Q. During single line working of DL the speed of the first train is ________ kmph
    A)15
    B)25
    C)20
    D)None of these
    Answer: 25
  • Q. The use of block instrument shall be governed by special instructions to be issued with the prior approval of
    A)CSO
    B)Railway Board
    C)CRS
    D)None of these
    Answer: CRS
  • Q. What will be maximum speed during shunting of goods train?
    A)25 kmph
    B)8 kmph
    C)15 kmph
    D)30 kmph
    Answer: 15 kmph
  • Q. Illuminated A marker of semi-automatic signal means ________.
    A)Outer signal
    B)Working as automatic signal
    C)Semi signal
    D)None of these
    Answer: Working as automatic signal
  • Q. What is the speed of a train after normalized in OHE supply immediate after tripping?
    A)40/15 kmph
    B)60/30 kmph
    C)35/20 kmph
    D)Normal speed
    Answer: 35/20 kmph
  • Q. When did the first ignition engine develop?
    A)1900
    B)1890
    C)1892
    D)1904
    Answer: 1892
  • Q. Competency certificate of the gateman of non- interlocked engineering gate is signed by ________.
    A)PWI
    B)CI
    C)LI
    D)TI
    Answer: PWI
  • Q. “C” class ODC is run with the permission of ________.
    A)Head Quarter
    B)DOM
    C)CRS
    D)None of these
    Answer: CRS
  • Q. For disconnection of points S&T official must issue form ________
    A)T/B 351
    B)T/351
    C)T/A 351
    D)None of these
    Answer: T/351