Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
A
30
B
20
C
10
D
None of these
Correct Answer
30
More Questions on Indian Railway
Q. Second train during all communication failure shall be dispatched after an interval of
A)35 B)20 C)25 D)30
Answer: 30
Q. Not more than ________ persons including trollyman shall go on a trolly.
A)9 B)10 C)3 D)4
Answer: 10
Q. A station where the rail lines end, is called
A)Block station B)Junction station C)Way - side station D)Terminal station
Answer: Terminal station
Q. The numbers of A, B and C coaches are 72, ________ and 76.
A)71 B)72 C)70 D)75
Answer: 70
Q. Maximum speed of trains during day in case of OHE failure is ________
A)65 km B)108 km C)70 km D)60 km
Answer: 60 km
Q. Diesel locomotives are built in?
A)Perambur B)Banglore C)Varanasi D)Hubli
Answer: Varanasi
Q. Dead engine is attached at ________ position on a Mail / Express train.
A)Both B)Engine to engine C)Next to engine D)None of these
Answer: Next to engine
Q. When the water rises above ballast level, but below rail level in cause ways, train may be permitted to run by
A)2 gangman B)JE(Pway) C)One gangman D)None of these
Answer: JE(Pway)
Q. Corridor block is mentioned in the ________.
A)SOR B)SWR C)WTT D)None of these
Answer: WTT
Q. With which country did India sign the Joint Declaration of Intent (JDI) to strengthen the cooperation on strategic projects in the field of Railways?
A)Germany B)Sweden C)Russia D)Italy
Answer: Germany
Q. When the section is occupied, the arrow indication in the panel in Twin single line working will be
A)No light B)White C)Red D)None of these
Answer: Red
Q. Where is the information about the Ruling Gradient of a section?
A)G & SR B)SWR C)WTT D)Operating Manual
Answer: WTT
Q. Adequate distance kept beyond the starter signal to take off the home signal is called as ________.
A)Block instrument B)Signal over lap C)Over lap D)None of these
Answer: Signal over lap
Q. How many dead engine can be attached in a goods train?
A)3 B)1 C)2 D)4
Answer: 1
Q. Stop signal is to be passed in On position.
A)T-806 B)T-509 C)T-369(3b) D)Simple memo
Answer: T-369(3b)
Q. Danger zone in 1500 DC traction is ________ meters from OHE.
A)3 B)1 C)2 D)4
Answer: 1
Q. During accident or Engine failure in the mid section the report sent to SM must be signed by ________.
A)Both B)GDR C)TDR D)None of these
Answer: GDR
Q. Maximum of ________ cranes can be attached in a passenger train.
A)3 B)1 C)2 D)4
Answer: 1
Q. What is the position of the Indian Railway under the zonal system?
A)Third B)First C)Second D)Forth
Answer: Second
Q. How much overlap is required to be off an Automatic stop signal on double line Automatic block system?