Q. Length of a BG ICF Coach is

Correct Answer

21.337 meters

More Questions on Indian Railway

  • Q. SLB determines the limits of Station section and ________
    A)Station Limit
    B)Block Section
    C)Station Section
    D)None of these
    Answer: Block Section
  • Q. In diesel engine, ignition is caused by
    A)Compression
    B)Spark
    C)Automatic starter
    D)Friction
    Answer: Compression
  • Q. Target time for dispatch of ARME from single exit siding at night is ________ minutes.
    A)8
    B)10
    C)5
    D)25
    Answer: 25
  • Q. When the train is stopped at FSS for more than ________ minutes, the Driver must send his assistant to station after consulting with guard.
    A)10
    B)5
    C)7
    D)None of these
    Answer: 5
  • Q. Length of a BG ICF Coach is
    A)21.337 meters
    B)22.089 meters
    C)21.494 meters
    D)None of these
    Answer: 21.337 meters
  • Q. The zone with the minimum length is
    A)South - East Railway
    B)North - Eastern Railway
    C)North - Eastern Frontier Railway
    D)South - Central Railway
    Answer: North - Eastern Frontier Railway
  • Q. In case of train parting ________ bell code is given on block instrument.
    A)000000-000
    B)00000-0
    C)000000-0
    D)0000-00
    Answer: 000000-000
  • Q. ________ bogies can be attached in rear of SLR of Mail/Express train.
    A)2
    B)4
    C)3
    D)8
    Answer: 2
  • Q. How much time a railway employee associated with train operation can not drink alcohol before coming to his work?
    A)6 hours
    B)12 hours
    C)8 hours
    D)2 Hours
    Answer: 8 hours
  • Q. How many systems of working in Indian Railways for train operation?
    A)8
    B)6
    C)7
    D)9
    Answer: 6
  • Q. Which authority shall be received to perform shunting beyond LSS at station of double line equipped with
    A)T/A 602
    B)T-806
    C)T/A 802
    D)T-806 A
    Answer: T-806
  • Q. Where the caution indicator placed in BG if the engineering work is more than one days and train not to be require to stop at site?
    A)800 Meter
    B)1200 Meter
    C)1000 Meter
    D)500 Meter
    Answer: 800 Meter
  • Q. All automatic stop signals will have ________ marker plate.
    A)G
    B)B
    C)A
    D)None of these
    Answer: A
  • Q. Apart from the regular store, Guard of material train must also possess ________.
    A)Third aid box
    B)First aid box
    C)Second aid box
    D)None of these
    Answer: First aid box
  • Q. If the passenger train is not arrived ________ minutes beyond its normal running time, it is treated as delayed train.
    A)4
    B)10
    C)9
    D)3
    Answer: 10
  • Q. Consider the following statements about Railway Convention Committee: 1)The Chairman of the Committee is appointed by the Speaker from amongst the members of the Committee 2) The Committee reviews the rate of dividend which is payable by the Railway Undertaking to the General Revenues Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: Both 1 & 2
  • Q. Shutting signal in the color light signal system under the starter of which light is visible in the on-condition?
    A)Single white
    B)Yellow
    C)Two White parallel
    D)No light
    Answer: No light
  • Q. Minimum depth of space for wheel flange from rail level in BG is
    A)3"
    B)2"
    C)1 (1/2)"
    D)None of these
    Answer: 1 (1/2)"
  • Q. In Automatic block system, when a train is working on T/B912, the speed over, points at station is
    A)20 kmph
    B)15 kmph
    C)10 kmph
    D)None of these
    Answer: 15 kmph
  • Q. For block forwarded form ________ must be issued.
    A)Both
    B)T/806+LSSS
    C)T/608
    D)None of these
    Answer: T/806+LSSS

Leave a Comment