- Q. Hand shunting of vehicles is prohibited in gradient
A)1 - 400 or steeper
B)1 - 260
C)1 - 400
D)None of these
Answer: 1 - 400 or steeper
- Q. On which authority advance starter may be passed during shunting operation in its on position?
A)On hand signal
B)T-369(3b)
C)Written memo
D)T-806
Answer: T-806
- Q. Length of a standard BG loop line is
A)720 meters
B)686 meters
C)670 meters
D)None of these
Answer: 686 meters
- Q. “Act” means the Railway Act is ________.
A)1989 (22 of 1989)
B)1989 (24 of 1989)
C)1989 (23 of 1989)
D)None of these
Answer: 1989 (24 of 1989)
- Q. In token territory, ________ is authority for shunting up to FSS.
A)T/806
B)Shunt Mental Token+T/806
C)Shunt Mental
D)None of these
Answer: Shunt Mental Token+T/806
- Q. During failure of signals and communications in DL automatic area the authority to proceed is
A)T/B 912
B)T/D 912
C)T/A 912
D)None of these
Answer: T/B 912
- Q. When ISMD attached train is allowed to run through on PF line the speed must be
A)10 kmph
B)5 kmph
C)8 kmph
D)None of these
Answer: 5 kmph
- Q. If loco pilot do not work in any section for more than a year, road learning for 2 trips by day and ________ trip by night is given.
A)3
B)1
C)2
D)4
Answer: 2
- Q. Minimum radius for curves in BG is
A)20°
B)16°
C)10°
D)None of these
Answer: 10°
- Q. In two aspects areas where shunting in the face of approaching train is not permitted, shunting can be permitted during ________ and under certain conditions (UP to FSS).
A)Both
B)Day
C)Night
D)None of these
Answer: Day
- Q. Block competency certificate is issued by ________.
A)AOM
B)Principal ZRTI
C)SM
D)None of these
Answer: Principal ZRTI
- Q. Who will be called Sahayak?
A)Coolies
B)New Superfast Train
C)Upcoming Event made for Disabled Persons
D)Railway Magazine (including Railway's upcoming ventures)
Answer: Coolies
- Q. when form T/D 912 is issued the driver shall not exceed the speed
A)25 kmph
B)15 kmph
C)20 kmph
D)None of these
Answer: 25 kmph
- Q. The main objective of British developing Indian Railway system was to facilitate the traffic between?
A)Source of raw material and production centers
B)Source of raw material and export centers
C)Source of raw material and ports
D)Source of raw material and markets
Answer: Source of raw material and production centers
- Q. Semi-automatic signal is identified by ________.
A)Illuminated a marker
B)Marker
C)Semi marker
D)None of these
Answer: Illuminated a marker
- Q. During total interruption of communication on SL , the speed of LE to establish communication during night is ________ kmph
A)5
B)10
C)20
D)None of these
Answer: 10
- Q. The time limit for starting BD special during day is ________.
A)30 meters
B)20 meters
C)15 meters
D)40 meters
Answer: 30 meters
- Q. Station limit is the portion between ________.
A)Both
B)Outermost signal
C)Innermost signal
D)None of these
Answer: Outermost signal
- Q. Sounding of 4 hooters means ________.
A)ART & MRV requirement at home Station
B)ART
C)MRV
D)None of these
Answer: ART & MRV requirement at home Station
- Q. Presentation of the first ever railway budget in India held in
A)1925
B)1853
C)1888
D)1905
Answer: 1925