More Questions on Indian Railway
- Q. The headquarter of Central Railway situated at?
A)Gwalior
B)Mumbai (CST)
C)Mumbai (Church Gate)
D)Gorakhpur
Answer: Mumbai (CST)
- Q. To admit the train on loop line, generally the far end points are to be ser for ________.
A)Both
B)Loop line
C)Main line
D)None of these
Answer: Main line
- Q. Speed of Train over points shall be ________ Km/h when the points are clamped and padlocked after disconnection of points.
A)30
B)20
C)25
D)15
Answer: 15
- Q. Diesel locomotives are built in?
A)Perambur
B)Banglore
C)Varanasi
D)Hubli
Answer: Varanasi
- Q. Motor Trolly can follow another motor trolly during
A)Day and Night clear weather
B)Day and Night
C)Day only
D)None of these
Answer: Day and Night clear weather
- Q. Derailment will come under accident class ________.
A)C
B)A
C)B
D)D
Answer: D
- Q. Signal failure advised to the driver through the station in rear will be inform
A)T/369(3b)
B)T/369
C)T/370
D)None of these
Answer: T/369
- Q. Which train in India has the longest route length?
A)Kanyakumari - Dibrugarh Vivek Express
B)Howrah - Jammu Tawi Himgiri Express
C)Kanyakumari - Jammu Tawi Himsagar Express
D)Guwahati - Tiruvananthapuram Express
Answer: Kanyakumari - Dibrugarh Vivek Express
- Q. If any Loco pilot leave from his duty place without to informed to his supervisor, it is treated as?
A)A & B both
B)Absent from his duty
C)Indiscipline
D)None of these
Answer: Absent from his duty
- Q. The largest national enterprise of India is
A)Airways
B)Indian Railway
C)Indian Shipyard
D)Waterways
Answer: Indian Railway
- Q. Guard of goods train shall sign on ________ minutes before the actual departure of the train.
A)40
B)45
C)30
D)35
Answer: 45
- Q. When the Head light fails during night the speed of train is ________ in BG. If there is no other caution for less speed is the Block section
A)25 kmph
B)30 kmph
C)40 kmph
D)None of these
Answer: 40 kmph
- Q. Block instrument and Advanced starter being failed after line clear?
A)T-369(3B) with P. NO. of line clear
B)T/C 1425
C)T/D 602 + T-511
D)T/D 1425
Answer: T-369(3B) with P. NO. of line clear
- Q. To start a train from unsignalled line ________ authority is issued.
A)T/511
B)T/512
C)T/515
D)T/521
Answer: T/511
- Q. DRM nominates ________ for each section to issue caution orders to train crew.
A)Nil notice
B)Caution notice station
C)Notice
D)None of these
Answer: Caution notice station
- Q. Is general manager responsible for?
A)Both railway Board and Railway Ministry
B)Railway Board
C)Railway Ministry
D)None of these
Answer: Railway Board
- Q. In which country was flange wheel invented?
A)Europe
B)Germany
C)Japan
D)Russia
Answer: Germany
- Q. How many systems of working in Indian Railways for train operation?
A)8
B)6
C)7
D)9
Answer: 6
- Q. Consider the following steps in Budget Procedure in India: 1)The demands for grants of various ministries and departments including railways are considered by the concerned standing committees 2)Broad contours of the budget and the principles and policies underlying it are discussed. 3)A cut motion is moved in the Lok Sabha 4)Budget is presented in the House. Which among the following is the correct sequence of the above steps?
A)4 2 1 3
B)1 2 3 4
C)1 2 4 3
D)3 1 4 2
Answer: 4 2 1 3
- Q. Maximum speed of trains during day in case of OHE failure is ________
A)65 km
B)108 km
C)70 km
D)60 km
Answer: 60 km