Q. What is the maximum speed of a train while view is obstructed due to thick and foggy weather?

Correct Answer

60 kmph

More Questions on Indian Railway

  • Q. If the block instrument becomes defective on a double line, ________ signal is also treated as defective.
    A)Stop signal
    B)Fisrt Stop signal
    C)Last stop signal
    D)None of these
    Answer: Last stop signal
  • Q. D class stations are called as ________.
    A)Station Limit
    B)Halt Station
    C)Class station
    D)None of these
    Answer: Halt Station
  • Q. All automatic stop signals will have ________ marker plate.
    A)G
    B)B
    C)A
    D)None of these
    Answer: A
  • Q. Target time for departing ART during day is 30 minutes and during night is ________ minutes.
    A)60
    B)40
    C)50
    D)45
    Answer: 45
  • Q. In case of block forward, private number of ________ station is written on shunting authority.
    A)T/809
    B)T/806
    C)T/809
    D)T/810
    Answer: T/806
  • Q. In token territory, ________ is authority for shunting up to FSS.
    A)T/806
    B)Shunt Mental Token+T/806
    C)Shunt Mental
    D)None of these
    Answer: Shunt Mental Token+T/806
  • Q. Number of the Nil caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 408
    D)None of these
    Answer: T/A 409
  • Q. Hand shunting outside section in gradient ________ is prohibited except with DRM permission.
    A)ST 1-800
    B)ST 1-600
    C)ST 1-700
    D)None of these
    Answer: ST 1-600
  • Q. Cancellation facility through ________ helpline number will be provided using ‘One Time Password’ sent on registered phone number.
    A)139
    B)144
    C)123
    D)119
    Answer: 139
  • Q. The headquarter of Central Railway situated at?
    A)Gwalior
    B)Mumbai (CST)
    C)Mumbai (Church Gate)
    D)Gorakhpur
    Answer: Mumbai (CST)
  • Q. For disconnection of points S&T official must issue form ________
    A)T/B 351
    B)T/351
    C)T/A 351
    D)None of these
    Answer: T/351
  • Q. During hand shunting only ________ Bogies can be hand shunted.
    A)3
    B)1
    C)2
    D)None of these
    Answer: 1
  • Q. Modified lower quadrant signaling may be introduced only with section of
    A)GM
    B)Railway Board
    C)CRS
    D)None of these
    Answer: CRS
  • Q. Which authority shall be issued to pass a starter signal during advanced starter single is failed and starter is interlocked with Ad. Starter at a station equipped with single line token less block?
    A)Memo + Hand Signal
    B)T-369(3b)
    C)PLCT
    D)Starter should be taken off
    Answer: T-369(3b)
  • Q. How much block overlap is required at the station equipped with single line MACLS?
    A)120 meters
    B)400 meters
    C)180 meters
    D)Zero meters
    Answer: 180 meters
  • Q. Station Master shall give line clear with ________ while granting line clear.
    A)Calling-on
    B)Shunt signal
    C)Private No.
    D)None of these
    Answer: Private No.
  • Q. For ‘B’ Class ISMD load, permission must be granted by
    A)CE
    B)DRM
    C)CRS
    D)None of these
    Answer: CE
  • Q. Colour of the semaphore calling on signal is ________.
    A)Green
    B)Red
    C)White
    D)None of these
    Answer: White
  • Q. Not more than ________ officials can travel in the locomotive unless authorised by operating official.
    A)3
    B)2
    C)4
    D)6
    Answer: 3
  • Q. Danger zone in 1500 DC traction is ________ meters from OHE.
    A)3
    B)1
    C)2
    D)4
    Answer: 1