Q. When the signal is blank in MACLS system, it is treated as showing ________ aspect.

Correct Answer

Most restricted

More Questions on Indian Railway

  • Q. The headquarters of Northern Railway is at
    A)Gorakhpur
    B)New Delhi
    C)Guwahati
    D)Mumbai (CST)
    Answer: New Delhi
  • Q. To apply for Line block, the notice shall be given to DRM not less than
    A)12 hours
    B)48 hours
    C)24 hours
    D)None of these
    Answer: 24 hours
  • Q. When the SM receive a message from local authorities fro unsafe condition of river bunds he must issue caution order with speed ________ kmph during day.
    A)5
    B)15
    C)20
    D)None of these
    Answer: 15
  • Q. Reminder Caution Order is?
    A)T/B409
    B)T/409
    C)T/A409
    D)None of these
    Answer: T/B409
  • Q. Capacity of a slip siding is ________
    A)06 or 07 wagon
    B)03 or 04 wagon
    C)04 or 05 wagon
    D)None of these
    Answer: 03 or 04 wagon
  • Q. What is the speed of a train after normalized in OHE supply immediate after tripping?
    A)40/15 kmph
    B)60/30 kmph
    C)35/20 kmph
    D)Normal speed
    Answer: 35/20 kmph
  • Q. By whom the rear portion of train left behind in block section protected?
    A)By engineearing official
    B)By Guard
    C)By LP
    D)No need to protect the load
    Answer: By Guard
  • Q. The train has parted
    A)_____00
    B)------0------0
    C)0___0
    D)00___
    Answer: ------0------0
  • Q. Normally material train will work during ________.
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. At Terminal yards where the signal overlap is zero, the speed over facing points is ________ kmph
    A)10
    B)20
    C)30
    D)None of these
    Answer: 10
  • Q. Modified lower quadrant signaling may be introduced only with section of
    A)GM
    B)Railway Board
    C)CRS
    D)None of these
    Answer: CRS
  • Q. Block section limit board provided at station?
    A)B class Single line TA
    B)B class Single line MAUQ
    C)B class Double line TA
    D)B class Double line MA
    Answer: B class Double line MA
  • Q. If position light shunt signal is placed below a stop signal, it shows ________ light in on condition.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. In Automatic block system, when a train is working on T/B912, the speed over, points at station is
    A)20 kmph
    B)15 kmph
    C)10 kmph
    D)None of these
    Answer: 15 kmph
  • Q. There is insufficient vacuum/pressure in engine.
    A)_____00
    B)___0___
    C)0___0
    D)00-----
    Answer: 00-----
  • Q. Single line working inforce on double line.
    A)T/D 602
    B)T-511
    C)T-512
    D)Simple memo
    Answer: T/D 602
  • Q. Water over track is 90 mm.
    A)15 kmph
    B)8 kmph
    C)10 kmph
    D)25 kmph
    Answer: 10 kmph
  • Q. Which Zone is the largest railway zone in India?
    A)Eastern Railway
    B)Central Railway
    C)Northern Railway
    D)Western Railway
    Answer: Northern Railway
  • Q. Ruling gradient of the division is mentioned in the ________.
    A)SOR
    B)SWR
    C)WTT
    D)None of these
    Answer: WTT
  • Q. During Thick or Foggy weather, 2 Detonators must be placed in rear of Engineering indicator at
    A)400 meters
    B)270 meters
    C)90 meters
    D)None of these
    Answer: 90 meters

Leave a Comment