Q. Which authority shall be received from station in rear to pass defective home signal?

Correct Answer

T-369(1)

More Questions on Indian Railway

  • Q. Who is the current director general of Railway Protection Force (RPF)?
    A)Dharmendra Kumar
    B)Brij Mohanty
    C)S H Prakash
    D)Arun Kumar
    Answer: Arun Kumar
  • Q. Block overlap in two aspect signalling system is ________ meters.
    A)400
    B)500
    C)600
    D)600
    Answer: 400
  • Q. The speed of Motor Trolly over points and crossings is
    A)15 kmph
    B)10 kmph
    C)8 kmph
    D)None of these
    Answer: 15 kmph
  • Q. What is the maximum speed of a train Ist train dispatched after introduced TSL on double line section?
    A)15 kmph
    B)30 kmph
    C)25 kmph
    D)Normal speed
    Answer: 25 kmph
  • Q. On DL in ________ minutes gap trains must be started during total interruption of communication.
    A)30
    B)20
    C)10
    D)None of these
    Answer: 30
  • Q. Distance between outer and home signals on a single line is ________ meters when there is no advanced starter or SLB in the opposite direction.
    A)400
    B)900
    C)800
    D)700
    Answer: 400
  • Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
    A)Block sectiond
    B)Next whole block section
    C)Back whole block section
    D)None of these
    Answer: Next whole block section
  • Q. When was the Jammu City appeared on the map of Indian Railway?
    A)1967
    B)1956
    C)1963
    D)1965
    Answer: 1965
  • Q. All the authorities related to TSL working are examined by TI and its report is submitted to DRM within ________ days of resumption of normal working.
    A)10
    B)7
    C)9
    D)15
    Answer: 7
  • Q. Derailment will come under accident class ________.
    A)C
    B)A
    C)B
    D)D
    Answer: D
  • Q. When a stream engine is running tender foremost the speed shall not exceed ________.
    A)30 kmph
    B)40 kmph
    C)20 kmph
    D)None of these
    Answer: 40 kmph
  • Q. If the advanced starter and IBS are defective, SM shall issue T/369(3b) authority with private number of ________ station to pass both advanced starter and IBS.
    A)Both
    B)Back
    C)Next
    D)None of these
    Answer: Next
  • Q. At A class station, Neutral zone is the portion between starter and ________ signal.
    A)Home signal
    B)Advance starter
    C)Starter
    D)None of these
    Answer: Advance starter
  • Q. All automatic stop signals will have ________ marker plate.
    A)G
    B)B
    C)A
    D)None of these
    Answer: A
  • Q. During Thick or Foggy weather, 2 Detonators must be placed in rear of Engineering indicator at
    A)400 meters
    B)270 meters
    C)90 meters
    D)None of these
    Answer: 90 meters
  • Q. WTT will be issued ________.
    A)Three in Year
    B)Once in a Year
    C)Two in a Year
    D)None of these
    Answer: Once in a Year
  • Q. If position light shunt signal is placed below a stop signal, it shows ________ light in on condition.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. What is the width of broad gauge railway line in India?
    A)4 feet 11 inches
    B)5 feet 3 inches
    C)5 feet 6 inches
    D)5 feet 4 inches
    Answer: 5 feet 6 inches
  • Q. Signal sighting committee shall submit its report on form ________.
    A)T/101 B
    B)T/103 B
    C)T/102 B
    D)None of these
    Answer: T/102 B
  • Q. ndian Railway’s Jamalpur Workshop is located at?
    A)Bihar
    B)West Bengal
    C)Orissa
    D)Uttar Pradesh
    Answer: Bihar