Q. Which is the least signalto be installed on C class stations in multiple aspect signalling?

Correct Answer

Distant, Home

More Questions on Indian Railway

  • Q. During thick & foggy weather, line must be clear upto ________ for granting line clear at a B’ class station in TALQ signalling system on Double line.
    A)Shunt signal
    B)Calling-on Signal
    C)Home Signal
    D)None of these
    Answer: Home Signal
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. In automatic area, when all signals and communications have failed, the driver is issued ________ as authority to proceed.
    A)T/A-912
    B)T/B-912
    C)T/C-912
    D)None of these
    Answer: T/B-912
  • Q. Which of the following ran the first train from Bori Bunder to Thane in 1853?
    A)Central India Railway
    B)Bombay Baroda Railway
    C)The Scindia Railway
    D)Great Indian Peninsula Railway
    Answer: Great Indian Peninsula Railway
  • Q. In case of block forward, private number of ________ station is written on shunting authority.
    A)T/809
    B)T/806
    C)T/809
    D)T/810
    Answer: T/806
  • Q. In Material train, vehicles shall not be detached on gradient.
    A)1-400
    B)ST 1-260
    C)1-100 or steeper
    D)None of these
    Answer: 1-100 or steeper
  • Q. Which authority shall be issued to pass a starter signal during advanced starter single is failed and starter is interlocked with Ad. Starter at a station equipped with single line token less block?
    A)Memo + Hand Signal
    B)T-369(3b)
    C)PLCT
    D)Starter should be taken off
    Answer: T-369(3b)
  • Q. When did the first ignition engine develop?
    A)1900
    B)1890
    C)1892
    D)1904
    Answer: 1892
  • Q. The railway station situated in the extreme south is
    A)Kanyakumari
    B)Chennai
    C)Cochin
    D)Trivandrum
    Answer: Kanyakumari
  • Q. Motor coach is a ________ coach.
    A)Self Minor
    B)Self Propelled
    C)Self System
    D)None of these
    Answer: Self Propelled
  • Q. Maximum speed of tower wagon is ________ km/h.
    A)40
    B)25
    C)20
    D)50
    Answer: 40
  • Q. Speed of the last train during ACF on double line is ________ km/h.
    A)20/15/Walking
    B)25/10/Walking
    C)20/10/Walking
    D)None of these
    Answer: 25/10/Walking
  • Q. What will be the maximum speed of a train hauling by Diesel engine when water level is 70mm above from rail level in broad guage line?
    A)5 km
    B)25 km
    C)15 km
    D)Stop Train
    Answer: 5 km
  • Q. ________ and ‘C’ class ODC shall not be crossed in the block section on double line.
    A)60
    B)50
    C)40
    D)75
    Answer: 40
  • Q. Loco and traffic running staff are eligible for ________ hours rest at Head quarters after running duty of less than 08 hours.
    A)12 Hours
    B)06 Hours
    C)10 Hours
    D)None of these
    Answer: 12 Hours
  • Q. Joint sighting committee shall inspect the visibility of signals once in
    A)6 months
    B)A month
    C)3 months
    D)None of these
    Answer: 3 months
  • Q. SLB determines the limits of Station section and ________
    A)Station Limit
    B)Block Section
    C)Station Section
    D)None of these
    Answer: Block Section
  • Q. In case of accident, siren is repeated at an interval of ________ minutes.
    A)20
    B)10
    C)15
    D)5
    Answer: 5
  • Q. When a train is working on T/D912 in automatic block in system, the train must be piloted into the station during reception by
    A)T/369(1)
    B)T/369(3b)
    C)T/369(2)
    D)T/409
    Answer: T/409
  • Q. If warner signal of any station becomes defective in off condition, ________ is issued to Loco Pilot from the station in rear.
    A)Verbally
    B)Walkie-Talkie
    C)Written Memo
    D)None of these
    Answer: Written Memo