Q. The maximum speed of the assistance train to be sent on T/A 602

Correct Answer

15 kmph

More Questions on Indian Railway

  • Q. Block instrument and Advanced starter being failed after line clear?
    A)T-369(3B) with P. NO. of line clear
    B)T/C 1425
    C)T/D 602 + T-511
    D)T/D 1425
    Answer: T-369(3B) with P. NO. of line clear
  • Q. Staff of ________ department shall protect the material train while working in block section.
    A)Engineering
    B)Operation
    C)C & W
    D)None of these
    Answer: Engineering
  • Q. Not more than ________ persons including trollyman shall go on a 4 HP motor trolly.
    A)9
    B)10
    C)7
    D)4
    Answer: 7
  • Q. When the points are set for main line, point indicator shows white target by day and ________ Light by night.
    A)Yellow
    B)Red
    C)Green
    D)White
    Answer: White
  • Q. When the train enters the block section without ATP, to permit to start the Train, SM to issue restarting memo with ________.
    A)Both
    B)PN
    C)Without PN
    D)None of these
    Answer: PN
  • Q. What is the massage of 000 (three short) whistle sound by loco pilot?
    A)Train parting
    B)Signal Approaching
    C)Train out of control
    D)Unable to proceed
    Answer: Train out of control
  • Q. Between which of the destinations the first Indian train was started?
    A)From Mumbai to Surat
    B)From Kolkata to Delhi
    C)From Mumbai to Thane
    D)From Mumbai to Madras
    Answer: From Mumbai to Thane
  • Q. Consider the following statements about the proposed Rail Development Authority: 1)It will act within the parameters of the Railway Act, 1989 2)The authority will consist of four members 3)It will regulate the sector opened to the private sector for investment Which of the above statements is/are correct?
    A)2 & 3 Only
    B)1 & 2 Only
    C)3 Only
    D)1, 2 & 3
    Answer: 1, 2 & 3
  • Q. A platform surrounded by rail lines from all the four sides, is called
    A)Island platform
    B)Dock platform
    C)Passenger platform
    D)Goods platform
    Answer: Island platform
  • Q. The headquarters of South Railways is situated at
    A)Delhi
    B)Kolkata
    C)Chennai
    D)Mumbai
    Answer: Chennai
  • Q. Signals are normally located to the ________ side of the line.
    A)Both
    B)Right
    C)Left
    D)None of these
    Answer: Left
  • Q. At the starting station, passenger train must have ________ kg/cm2 of FP pressure and 4.8 kg/cm2 of BP pressure in the brake van.
    A)5
    B)4
    C)2
    D)8
    Answer: 5
  • Q. During TSL working in thick and foggy weather, speed of the first train shall not exceed ________ km/h.
    A)15 km
    B)8 km
    C)10 km
    D)25 km
    Answer: 25 km
  • Q. Maximum No. of ________ coaches can be attached in rear of SLR of passenger train.
    A)4
    B)2
    C)3
    D)6
    Answer: 2
  • Q. If a staff is absent for ________ days from duty fresh declaration must be obtained
    A)20 days
    B)10 days
    C)15 days
    D)None of these
    Answer: 15 days
  • Q. When the train catches fire, that carriage must be ________.
    A)Both
    B)Isolated
    C)Non-isolated
    D)None of these
    Answer: Isolated
  • Q. Station Working Rules of Non-interlocked station is signed by ________.
    A)AOM & ADEN
    B)DOM & DEN
    C)Sr. DOM & Sr. DEN
    D)None of these
    Answer: Sr. DOM & Sr. DEN
  • Q. Who of the following was the first Railway Minister of independent India?
    A)Jawaharlal Nehru
    B)John Mathai
    C)Lal Bahadur Shastri
    D)Shanmugham Shetty
    Answer: John Mathai
  • Q. Mountain Railways of India refer to the railway lines built in the mountains of India in the nineteenth and early twentieth century, during the British Raj, even being run today by the Indian Railways. How many railway lines refer to the Mountain Railways of India ?
    A)5
    B)3
    C)4
    D)6
    Answer: 3
  • Q. Distant signal is a ________ signal.
    A)Subsidiary
    B)Permissive
    C)Home
    D)None of these
    Answer: Permissive

Leave a Comment