More Questions on Indian Railway
- Q. Fog signal man must be on ________ Hrs duty.
A)5
B)3
C)4
D)None of these
Answer: 3
- Q. If the G marker Gate signal is at ON, Loco pilot may pass it after stopping for 01 minute by day and ________ minutes by night.
A)8
B)5
C)2
D)4
Answer: 2
- Q. Isolation shall be provided at an interlocked station when the speed is
A)Above 50 kmph
B)50 kmph
C)75 kmph
D)None of these
Answer: Above 50 kmph
- Q. At a C’ class staion in two aspect signalling system, ________ and home signals are provided.
A)Sectional
B)Corner
C)Warner
D)None of these
Answer: Warner
- Q. Distant signal is a ________ signal.
A)Subsidiary
B)Permissive
C)Home
D)None of these
Answer: Permissive
- Q. What is maximum width for 8-Wheeled Goods stock in BG?
A)3250 mm
B)3050 mm
C)3200 mm
D)3300 mm
Answer: 3050 mm
- Q. The Indian Railways has launched which virtual server to optimise server usage and faster connectivity?
A)RailSilver
B)RailSagar
C)RailCloud
D)RailBharat
Answer: RailCloud
- Q. Notice station caution order No. is ________
A)T/C-409
B)T/409
C)T/B-409
D)None of these
Answer: T/409
- Q. Which of the following zones administers the Matheran Hill Railway?
A)Central Railways
B)Konkan Railways
C)Western Railways
D)Southern Railways
Answer: Central Railways
- Q. Nil Caution order number is ________
A)T/C409
B)T/A-409
C)T/B-409
D)None of these
Answer: T/A-409
- Q. During serious accident, ________ will be the in-charge of control office.
A)Sr. DOM
B)DOM
C)AOM
D)None of these
Answer: Sr. DOM
- Q. When two trollies are working in section the gap between the two must be
A)400 Meters
B)100 meters
C)200 meters
D)None of these
Answer: 100 meters
- Q. Where is the Research, Design and Standard Organisation situated?
A)Pune
B)Lucknow
C)Bangalore
D)New Delhi
Answer: Lucknow
- Q. Besides Mahrashtra, Karnataka and Goa, which of the following is the fourth State for Konkan Railway Project?
A)Gujarat
B)Kerala
C)Tamil Nadu
D)Andhra Pradesh
Answer: Kerala
- Q. The manufacturing of steam engine in Chittranjan Locomotive Works was stopped in
A)1972
B)1974
C)1961
D)1973
Answer: 1972
- Q. When the driver reports rough running or lurch on the run, the SM to issue caution order with speed ________ kmph
A)20
B)10
C)15
D)None of these
Answer: 10
- Q. On which place the competent Railway servant shall be appointed to show proceed hand signal while receive a train on obstructed line on calling-on signal?
A)45 meters beyond the obstruction
B)At 1st facing point of station
C)Facing point of concern line
D)No need
Answer: 45 meters beyond the obstruction
- Q. If outside the station limits the distance between two trains is ________ in averted collusion, such occurrence may not be treated as an averted collision.
A)100 meter
B)200 meter
C)250 meter
D)400 meters and more
Answer: 400 meters and more
- Q. During shunting of a passenger train the train engine will be stopped ________ mtrs before attaching to load?
A)10 meters
B)20 meters
C)15 meters
D)5 meters
Answer: 20 meters
- Q. At the starting station, passenger train must have ________ kg/cm2 of FP pressure and 4.8 kg/cm2 of BP pressure in the brake van.
A)5
B)4
C)2
D)8
Answer: 5