More Questions on Indian Railway
- Q. If the Advanced starter is defective and IBS is working, SM shall issue ________ authority with private number of same station to pass the advanced starter.
A)T/369(4b)
B)T/369(3b)
C)T/369(2B)
D)T/369(5b)
Answer: T/369(3b)
- Q. TSL is started between those two stations at which cross over facility are available and
A)D Class/IBC
B)A Class/IBS
C)C Class/IBS
D)None of these
Answer: C Class/IBS
- Q. Signal that controls the entry of trains into the block section in advance is called as
A)Last Stop signal
B)Fisrt Stop signal
C)Stop signal
D)None of these
Answer: Last Stop signal
- Q. Matheran Hill Railway is a narrow gauge heritage railway located in which state?
A)Maharashtra
B)Tamil Nadu
C)Himachal Pradesh
D)Meghalaya
Answer: Maharashtra
- Q. Which Zone is the largest railway zone in India?
A)Eastern Railway
B)Central Railway
C)Northern Railway
D)Western Railway
Answer: Northern Railway
- Q. Headquarters of which one among the following Railway Zones in India is situated at the highest elevation from the mean sea level?
A)South Western Railway
B)East Central Railway
C)South Eastern Railway
D)West Central Railway
Answer: South Western Railway
- Q. ISMD must be attached always
A)In the middle
B)Next to Engine
C)In rear
D)None of these
Answer: Next to Engine
- Q. What is the maximum speed of a goods train pushed backed from block section ?
A)15/8 kmph
B)15 kmph
C)8 kmph
D)None of these
Answer: 8 kmph
- Q. Number of train signal register of double line is ________.
A)T/66 B
B)T/66 A
C)T/66 C
D)T/66
Answer: T/66 B
- Q. With respect to ‘Operating ratio’ in Railways, which of the following statement is/are correct? 1)The higher is the ‘Operating Ratio’; the better is the economic condition of railways. 2) ‘Operating ratio’ of Indian Railways is high on account of social service obligation imposed in Budget. Select the correct option from the codes given below
A)Both 1 & 2
B)Only 1
C)Only 2
D)Neither 1 nor 2
Answer: Only 2
- Q. Not more than ________ persons including trollyman shall go on a trolly.
A)9
B)10
C)3
D)4
Answer: 10
- Q. Number of the caution order is ________
A)T/410
B)T/409
C)T/408
D)None of these
Answer: T/409
- Q. DRM nominates ________ for each section to issue caution orders to train crew.
A)Nil notice
B)Caution notice station
C)Notice
D)None of these
Answer: Caution notice station
- Q. When the train has not cleared the fouling marks. Driver to give ________ whistle
A)01 long
B)03 long
C)02 long
D)None of these
Answer: 03 long
- Q. Stop signal is to be passed in On position.
A)T-806
B)T-509
C)T-369(3b)
D)Simple memo
Answer: T-369(3b)
- Q. Signal sighting committee shall submit its report on form ________.
A)T/101 B
B)T/103 B
C)T/102 B
D)None of these
Answer: T/102 B
- Q. Time taken by train running at booked speed is called as ________.
A)Normal running time
B)Long time
C)Minimum running time
D)None of these
Answer: Normal running time
- Q. Loss of railway property of Rs. more than 2 Crores is treaed as ________ accident.
A)Both
B)Minor
C)Serious
D)None of these
Answer: Serious
- Q. Consider the following railway zones with their headquarters: West Central Railway→ Jabalpur East Coast Railway → Bhubaneswar Western Railway→ Mumbai Which of the above is / are correct?
A)1, 2 & 3
B)1 & 2 Only
C)2 & 3 Only
D)None
Answer: 1, 2 & 3
- Q. When the platform level is ________ MM and more second arriving train shall not be received and berthed on non platform line directly.
A)650
B)700
C)725
D)760
Answer: 760