More Questions on Indian Railway
- Q. When VP vehicles are attached in a goods train the maximum number of VPvehicle in one group is
A)8
B)10
C)6
D)None of these
Answer: 6
- Q. When the Head light fails during night the speed of train is ________ in BG. If there is no other caution for less speed is the Block section
A)25 kmph
B)30 kmph
C)40 kmph
D)None of these
Answer: 40 kmph
- Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.
A)LI
B)TI
C)CI
D)None of these
Answer: TI
- Q. The headquarters of the South Central Railway zone is located in?
A)Hyderabad
B)Kolkata
C)Secunderabad
D)Gorakhpur
Answer: Secunderabad
- Q. Who of the following is known for having designed the first railway timetables?
A)George Bradshaw
B)George Bradman
C)George Bernard Shaw
D)George Brummel
Answer: George Bradshaw
- Q. Consider the following statements about the Railway Convention Committee: 1)It consists of members from Lok Sabha only 2)Chairman of Railway Convention Committee is appointed by Lok Sabha speaker Which among the above statements is/are correct?
A)Both 1 & 2
B)1 Only
C)2 Only
D)Neither 1 nor 2
Answer: 2 Only
- Q. Normally the train with hot axle is admitted on ________.
A)Main Line
B)Loop Line
C)Siding Line
D)None of these
Answer: Main Line
- Q. If any Loco pilot leave from his duty place without to informed to his supervisor, it is treated as?
A)A & B both
B)Absent from his duty
C)Indiscipline
D)None of these
Answer: Absent from his duty
- Q. Which of the following ran the first train from Bori Bunder to Thane in 1853?
A)Central India Railway
B)Bombay Baroda Railway
C)The Scindia Railway
D)Great Indian Peninsula Railway
Answer: Great Indian Peninsula Railway
- Q. What type of speed restriction imposed for loco pilot when at LC gate communication not available between Gateman & Station Master ?
A)8 kmph
B)15 kmph
C)10 kmph
D)Normal
Answer: 10 kmph
- Q. In automatic areas when all signals have failed and communication is available, the driver is issued ________ as authority to proceed.
A)T/C-912
B)T/B-912
C)T/D-912
D)None of these
Answer: T/D-912
- Q. Maximum speed of trains during day in case of OHE failure is ________
A)65 km
B)108 km
C)70 km
D)60 km
Answer: 60 km
- Q. In case of continuous category/preparatory and /or complementary work between 15 and 45 meters should be treated as ________.
A)30 meters
B)20 meters
C)25 meters.
D)None of these
Answer: 30 meters
- Q. Derailment will come under accident class ________.
A)C
B)A
C)B
D)D
Answer: D
- Q. On which place the competent Railway servant shall be appointed to show proceed hand signal while receive a train on obstructed line on calling-on signal?
A)45 meters beyond the obstruction
B)At 1st facing point of station
C)Facing point of concern line
D)No need
Answer: 45 meters beyond the obstruction
- Q. Trap indicator is provided to indicate ________.
A)Provision Switch
B)Indication Switch
C)Derailing switch
D)None of these
Answer: Derailing switch
- Q. During single line working of DL the speed of the first train is ________ kmph
A)15
B)25
C)20
D)None of these
Answer: 25
- Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
A)Both 1 & 2
B)1 Only
C)2 Only
D)Neither 1 nor 2
Answer: 2 Only
- Q. During hand shunting only ________ Bogies can be hand shunted.
A)3
B)1
C)2
D)None of these
Answer: 1
- Q. The number of line clear ticket in down direction is ________.
A)T/A 1425
B)T/C 1425
C)T/D 1426
D)T/D 1425
Answer: T/D 1425