Q. In case of continuous category/preparatory and /or complementary work between 15 and 45 meters should be treated as ________.

Correct Answer

30 meters

More Questions on Indian Railway

  • Q. When signal is not visible from minimum sighting distance, ________ signal is provided.
    A)Shunt
    B)Repeating
    C)Call-on
    D)None of these
    Answer: Repeating
  • Q. If there is no advanced starter at A’ class station, signal overlap will be ________.
    A)Block sectiond
    B)Next whole block section
    C)Back whole block section
    D)None of these
    Answer: Next whole block section
  • Q. For work of long duration, the stop indicator must be erected at not less than
    A)40
    B)30
    C)50
    D)45
    Answer: 30
  • Q. When the calling on signal is taken off, it indicates the loco pilot to proceed ________ and be prepared to stop short of any obstruction.
    A)Defective
    B)Caution
    C)Cautiously
    D)None of these
    Answer: Cautiously
  • Q. What is the speed of A class ODC in BG?
    A)40 kmph
    B)15 kmph
    C)25 kmph
    D)Normal speed
    Answer: Normal speed
  • Q. Kacheguda railway station has declared the India’s first Energy – Efficient ‘A1 Category’ Railway Station. It is situated in which city?
    A)Kochi
    B)Hyderabad
    C)Chennai
    D)Kolkata
    Answer: Hyderabad
  • Q. In recent times, the “dynamic brake system” is becoming popular in modern railways. The dynamic brake system coverts Kinetic energy to________:
    A)Sound energy
    B)Potential energy
    C)Electricity
    D)Magnetic energy
    Answer: Electricity
  • Q. In Automatic Block system , in BG when there is obstruction in the adjacent line, driver to protect the adjacent line first by placing one detonator at not less than ________ , metres.
    A)1200
    B)600
    C)800
    D)None of these
    Answer: 600
  • Q. The extended life of Detonator is ________ Years.
    A)4
    B)5
    C)6
    D)10
    Answer: 10
  • Q. What will be the maximum speed of a train hauling by Diesel engine when water level is 70mm above from rail level in broad guage line?
    A)5 km
    B)25 km
    C)15 km
    D)Stop Train
    Answer: 5 km
  • Q. Number of the Reminder caution order is ________.
    A)T/C 410
    B)T/A 409
    C)T/B 409
    D)None of these
    Answer: T/B 409
  • Q. In case of train parting ________ bell code is given on block instrument.
    A)000000-000
    B)00000-0
    C)000000-0
    D)0000-00
    Answer: 000000-000
  • Q. Colour of the semaphore calling on signal is ________.
    A)Green
    B)Red
    C)White
    D)None of these
    Answer: White
  • Q. At the starting station, 40 BCN air braked train must have ________ kg/cm2 of BP pressure in the brake van.
    A)6.8
    B)7.8
    C)5.8
    D)4.8
    Answer: 4.8
  • Q. Shatabdi Express train was started in ________.
    A)1990
    B)1984
    C)1988
    D)1985
    Answer: 1988
  • Q. Loss of railway property of Rs. more than 2 Crores is treaed as ________ accident.
    A)Both
    B)Minor
    C)Serious
    D)None of these
    Answer: Serious
  • Q. In diesel engine, ignition is caused by
    A)Compression
    B)Spark
    C)Automatic starter
    D)Friction
    Answer: Compression
  • Q. Normally material train will work during ________.
    A)Both
    B)Day
    C)Night
    D)None of these
    Answer: Day
  • Q. In which country was flange wheel invented?
    A)Europe
    B)Germany
    C)Japan
    D)Russia
    Answer: Germany
  • Q. Caution and Termination indication Boards will be fixed from the bridge or vulnerable places at
    A)1000 meters
    B)400 meters
    C)600 meters
    D)None of these
    Answer: 600 meters