Q. When the water rises above ballast level, but below rail level in cause ways, train may be permitted to run by

Correct Answer

JE(Pway)

More Questions on Indian Railway

  • Q. When a train is received at a station during signal failure on signal post telephone, the speed of train is
    A)8 kmph
    B)15 kmph
    C)25 kmph
    D)None of these
    Answer: 15 kmph
  • Q. DRM nominates ________ for each section to issue caution orders to train crew.
    A)Nil notice
    B)Caution notice station
    C)Notice
    D)None of these
    Answer: Caution notice station
  • Q. Hand shunting of wagons is totally prohibited in gradients
    A)1 in 260
    B)1 in 400 OR Steeper
    C)ST 1- IN 400
    D)None of these
    Answer: 1 in 400 OR Steeper
  • Q. Capacity of a catch siding is ________.
    A)Station
    B)Equivalent to length of full train
    C)Length
    D)None of these
    Answer: Equivalent to length of full train
  • Q. Which is the India’s first double Decker train?
    A)Guwahati Thiruvananthapuram Express
    B)Ahmedabad - Mumbai Central Double Decker Express
    C)Samjhauta Express
    D)Howrah – Dhanbad Double Decker Express
    Answer: Howrah – Dhanbad Double Decker Express
  • Q. Length of BOXN Wagon is
    A)10.71 meters
    B)8.67 meters
    C)9.78 meters
    D)None of these
    Answer: 10.71 meters
  • Q. “Act” means the Railway Act is ________.
    A)1989 (22 of 1989)
    B)1989 (24 of 1989)
    C)1989 (23 of 1989)
    D)None of these
    Answer: 1989 (24 of 1989)
  • Q. During TFC on single line, when line clear is obtained for more than one train, trains are run at an interval of ________ minutes.
    A)35
    B)20
    C)25
    D)30
    Answer: 30
  • Q. Target time for ARME from double exit siding is?
    A)45 minutes
    B)20 minutes
    C)30 minutes
    D)60 minutes
    Answer: 20 minutes
  • Q. Warner signal is of ________ shape in TALQ signalling system.
    A)Both
    B)Fish Tailed
    C)Long
    D)None of these
    Answer: Fish Tailed
  • Q. WTT will be issued ________.
    A)Three in Year
    B)Once in a Year
    C)Two in a Year
    D)None of these
    Answer: Once in a Year
  • Q. When was the first underground railway (Metro Railway) started?
    A)1984
    B)1982
    C)1989
    D)1992
    Answer: 1984
  • Q. Train is to be started from non signalled line
    A)T/D 602
    B)T-511
    C)T-512
    D)Simple memo
    Answer: T-511
  • Q. Yearly goods stock census is taken on ________.
    A)30st November
    B)31st December
    C)31st October
    D)31st March
    Answer: 30st November
  • Q. Where is RDSO Situated.
    A)Chennai
    B)Vadodara
    C)Lucknow
    D)New Delhi
    Answer: Lucknow
  • Q. For Block Back form ________ To be issued on DL.
    A)T/B-806+PN
    B)T/806+PN
    C)T/A806+PN
    D)None of these
    Answer: T/806+PN
  • Q. Depot in-charge is responsible to test the detonators once in ________.
    A)Year
    B)Monthly
    C)Weekly
    D)None of these
    Answer: Year
  • Q. If position light shunt signal is placed below a stop signal, it shows ________ light in on condition.
    A)Green
    B)White
    C)Red
    D)NIL
    Answer: NIL
  • Q. While stabling box load, hand brakes of ________ wagons at both ends shall be pinned down.
    A)7 - 7
    B)8 - 8
    C)6 - 6
    D)8 - 8
    Answer: 6 - 6
  • Q. The minimum BP pressure is requiring on engine before continuity test is?
    A)5.8 kg/cm2 D. 5.00 kg/cm2
    B)4.8 kg/cm2 B. 6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
    C)6.00 kg/cm2 C. 5.8 kg/cm2 D. 5.00 kg/cm2
    D)5.00 kg/cm2
    Answer: 5.00 kg/cm2