Q. Block overlap in multiple aspect signalling system is ________ meters.

Correct Answer

180

More Questions on Indian Railway

  • Q. A separate Railway Budget, which is different from the General Budget, was first introduced in 1924 on the basis of recommendations of the 10 – member:
    A)Rail Budget Committee
    B)Acworth Committee
    C)Srinivas Shastri Committee
    D)Sultan Committee
    Answer: Acworth Committee
  • Q. Station Master shall give line clear with ________ while granting line clear.
    A)Calling-on
    B)Shunt signal
    C)Private No.
    D)None of these
    Answer: Private No.
  • Q. A lorry shall be protected by banner flags and detonators if it remains stationary within the station yard for more than
    A)20 meters
    B)15 meters
    C)10 meters
    D)None of these
    Answer: 15 meters
  • Q. Maximum impact speed when shunting a group of roller bearing fitted stock coupled together must be?
    A)3 kmph
    B)2 kmph
    C)2.5 kmph
    D)3.5 kmph
    Answer: 2.5 kmph
  • Q. At station where it is not possible to exchange the signal between Guard and Loco Pilot due to curvature the guard shall ask the LP to start the train on ________.
    A)Walkie-Talkie
    B)Walkie
    C)VHF
    D)None of these
    Answer: Walkie-Talkie
  • Q. Special instructions are issued by ________.
    A)Both
    B)COM
    C)Sr. DOM
    D)None of these
    Answer: COM
  • Q. When was the Central Railway established?
    A)14th April 1951
    B)5th Nov 1951
    C)14th Nov 1951
    D)16th August, 1951
    Answer: 5th Nov 1951
  • Q. On which authority advance starter may be passed during shunting operation in its on position?
    A)On hand signal
    B)T-369(3b)
    C)Written memo
    D)T-806
    Answer: T-806
  • Q. Signals are treated as ________ if connected points become defective.
    A)Both
    B)Defective
    C)Restricted
    D)None of these
    Answer: Defective
  • Q. Which state to have India’s first privately – run railway station?
    A)Kerala
    B)Tripura
    C)Odisha
    D)Madhya Pradesh
    Answer: Madhya Pradesh
  • Q. While receiving train on an obstructed line and danger signal must be shown to LP at
    A)40 meters from obstruction
    B)45 meters
    C)30 meters
    D)None of these
    Answer: 45 meters
  • Q. When the derailing switch is open, trap indicator shows red target by day and ________ Light by night.
    A)Yellow
    B)Red
    C)Green
    D)White
    Answer: Red
  • Q. SCOR maintains ________ register when serious accident occurs.
    A)Chronological
    B)Logical
    C)Un-logical
    D)None of these
    Answer: Chronological
  • Q. Consider the following statements about the Railwire Saathi project: 1)It is an initiative by the Indian Railway Stations Development Corporation Limited (IRSDC) 2)It aims to provide railway stations in India with high – speed public Wi – Fi service Which of the above statements is/are correct?
    A)Both 1 & 2
    B)1 Only
    C)2 Only
    D)Neither 1 nor 2
    Answer: 2 Only
  • Q. BP in the Guard cab of EMU shall be ________ kg/cm2 and Motor mans cab shall be 4.6 kg/cm2.
    A)4
    B)4.2
    C)4.01
    D)4.6
    Answer: 4.6
  • Q. ndian Railway’s Jamalpur Workshop is located at?
    A)Bihar
    B)West Bengal
    C)Orissa
    D)Uttar Pradesh
    Answer: Bihar
  • Q. Loco and traffic running staff are entitled for ________ hours rest at head quarters after running duty of 08 hours or more
    A)12 hours
    B)04 hours
    C)08 hours
    D)16 hours
    Answer: 16 hours
  • Q. Fly shunting will take place in
    A)Flat Yard
    B)Hump Yard
    C)Gravity Yard
    D)None of these
    Answer: Hump Yard
  • Q. Not more than ________ persons including trollyman shall go on a 4 HP motor trolly.
    A)9
    B)10
    C)7
    D)4
    Answer: 7
  • Q. What will be the maximum speed of a train hauling by Diesel engine when water level is 70mm above from rail level in broad guage line?
    A)5 km
    B)25 km
    C)15 km
    D)Stop Train
    Answer: 5 km