More Questions on Indian Railway
- Q. Between which of the destinations the first Indian train was started?
A)From Mumbai to Surat
B)From Kolkata to Delhi
C)From Mumbai to Thane
D)From Mumbai to Madras
Answer: From Mumbai to Thane
- Q. Single line working inforce on double line.
A)T/D 602
B)T-511
C)T-512
D)Simple memo
Answer: T/D 602
- Q. Maximum impact speed when shunting a single roller bearing fitted stock must be?
A)5 kmph
B)3 kmph
C)4 kmph
D)6 kmph
Answer: 5 kmph
- Q. Where was the B.B.C.I locomotive started?
A)Boriville
B)Jamalpur
C)Parel
D)Hyderabad
Answer: Parel
- Q. Nil Caution order number is ________
A)T/C409
B)T/A-409
C)T/B-409
D)None of these
Answer: T/A-409
- Q. Consider the following railway zones with their headquarters: West Central Railway→ Jabalpur East Coast Railway → Bhubaneswar Western Railway→ Mumbai Which of the above is / are correct?
A)1, 2 & 3
B)1 & 2 Only
C)2 & 3 Only
D)None
Answer: 1, 2 & 3
- Q. “Act” means the Railway Act is ________.
A)1989 (22 of 1989)
B)1989 (24 of 1989)
C)1989 (23 of 1989)
D)None of these
Answer: 1989 (24 of 1989)
- Q. In Material train, vehicles shall not be detached on gradient.
A)1-400
B)ST 1-260
C)1-100 or steeper
D)None of these
Answer: 1-100 or steeper
- Q. Number of train signal register of double line is ________.
A)T/66 B
B)T/66 A
C)T/66 C
D)T/66
Answer: T/66 B
- Q. BSLB determines the limits of block section and ________ .
A)Station Limit
B)Block Section
C)Station Section
D)None of these
Answer: Station Section
- Q. Goods warning board will be provided from FSS in BG at
A)560 meters
B)1400 meters
C)1000 meters
D)None of these
Answer: 1400 meters
- Q. Indian Railways which is the largest of the Public Sector Enterprises, is divided in how many regions?
A)8
B)7
C)9
D)10
Answer: 9
- Q. Target time for departing ART during day is 30 minutes and during night is ________ minutes.
A)60
B)40
C)50
D)45
Answer: 45
- Q. Consider the following: Road and Railways Schools Sanitary Facilities Hospitals Which among the above are considered to be the Economic Overheads?
A)1, 2 & 3
B)Only 1
C)1 & 2
D)1, 2 , 3 & 4
Answer: Only 1
- Q. On which authority advance starter may be passed during shunting operation in its on position?
A)On hand signal
B)T-369(3b)
C)Written memo
D)T-806
Answer: T-806
- Q. The maximum speed of the assistance train to be sent on T/A 602
A)30 kmph
B)10 kmph
C)15 kmph
D)40 kmph
Answer: 15 kmph
- Q. What is the maximum speed of a goods train pushed backed from block section ?
A)15/8 kmph
B)15 kmph
C)8 kmph
D)None of these
Answer: 8 kmph
- Q. Railway Staff College is situated at
A)Chennai
B)Bangalore
C)Secunderabad
D)Vadodara
Answer: Vadodara
- Q. While shunting a complete train from one line to the other, ________ shall be present in the brakevan.
A)ALP
B)Driver
C)Guard
D)None of these
Answer: Guard
- Q. After getting T/369(I) speed over the points while passing the signal is ________ km/h.
A)25
B)75
C)15
D)30
Answer: 15
- Geography
- History
- Indian Culture
- Indian Economy
- Indian Politics
- Indian Railway
- Sports