Q. Read the Following Railway Headquarters and Identify which is False?

Correct Answer

Central railway - Bhopal

More Questions on Indian Railway

  • Q. When the derailing switch is open, trap indicator shows red target by day and ________ Light by night.
    A)Yellow
    B)Red
    C)Green
    D)White
    Answer: Red
  • Q. With respect to ‘Operating ratio’ in Railways, which of the following statement is/are correct? 1)The higher is the ‘Operating Ratio’; the better is the economic condition of railways. 2) ‘Operating ratio’ of Indian Railways is high on account of social service obligation imposed in Budget. Select the correct option from the codes given below
    A)Both 1 & 2
    B)Only 1
    C)Only 2
    D)Neither 1 nor 2
    Answer: Only 2
  • Q. If the train passes through without headlight, SM shall give ________ bell code and advise the reason.
    A)0000-0
    B)000000-0
    C)00000-0
    D)0000-00
    Answer: 000000-0
  • Q. Which is the India’s first double Decker train?
    A)Guwahati Thiruvananthapuram Express
    B)Ahmedabad - Mumbai Central Double Decker Express
    C)Samjhauta Express
    D)Howrah – Dhanbad Double Decker Express
    Answer: Howrah – Dhanbad Double Decker Express
  • Q. When the train catches fire, that carriage must be ________.
    A)Both
    B)Isolated
    C)Non-isolated
    D)None of these
    Answer: Isolated
  • Q. The banner flag is a ________
    A)Both of these
    B)Temporary stop signal
    C)Permanent stop signal
    D)None of these
    Answer: Temporary stop signal
  • Q. “Act” means the Railway Act is ________.
    A)1989 (22 of 1989)
    B)1989 (24 of 1989)
    C)1989 (23 of 1989)
    D)None of these
    Answer: 1989 (24 of 1989)
  • Q. Shatabdi Express train was started in ________.
    A)1990
    B)1984
    C)1988
    D)1985
    Answer: 1988
  • Q. Which state government has recently signed MoU with Indian Railways to expand green cover?
    A)Maharashtra
    B)Kerala
    C)Uttar Pradesh
    D)Rajasthan
    Answer: Maharashtra
  • Q. Whistle boards must be provided at an adequate distance in rear of all level crossing gates on both side?
    A)600 meters
    B)400 meters
    C)500 meters
    D)800 meters
    Answer: 600 meters
  • Q. After TFC, all the related authorities are inspected by ________ and its report is sent to DRM within 7 days.
    A)LI
    B)TI
    C)CI
    D)None of these
    Answer: TI
  • Q. Which of the following zonal headquarters – city combination is incorrect?
    A)East Central - Hajipur
    B)South East Central - Bilaspur
    C)North Western - Jodhpur
    D)West Central - Jabalpur
    Answer: North Western - Jodhpur
  • Q. Over which of the following rivers is the world’s highest railway bridge in Kashmir being constructed?
    A)Sutlej
    B)Chenab
    C)Jhelum
    D)Indus
    Answer: Chenab
  • Q. Speed of the last train during ACF on double line is ________ km/h.
    A)20/15/Walking
    B)25/10/Walking
    C)20/10/Walking
    D)None of these
    Answer: 25/10/Walking
  • Q. Duplicate signal is ________.
    A)Co-acting signal
    B)Home Signal
    C)Warner Signal
    D)None of these
    Answer: Co-acting signal
  • Q. Section controller is responsible for ________ on a section of a railway provided with the system of speech communication.
    A)Station Traffic
    B)Movement of traffic
    C)None of Traffic
    D)None of these
    Answer: Movement of traffic
  • Q. Loco Pilot shall sound _________ whistle to acknowledge the Guard hand signal.
    A)Three Long
    B)One Long
    C)Two Long
    D)None of these
    Answer: One Long
  • Q. Motor Trolley permit is ________
    A)T/1625
    B)T/1425
    C)T/1525
    D)None of these
    Answer: T/1525
  • Q. In automatic block area SL. The LSS shall not be taken of unless the line is clear upto
    A)Automatic stop signal+180 Meters
    B)next automatic stop signal
    C)Automatic stop signal+120 Meters
    D)None of these
    Answer: next automatic stop signal
  • Q. The train has parted
    A)_____00
    B)------0------0
    C)0___0
    D)00___
    Answer: ------0------0

Leave a Comment